Columbia Place has contracted with Medrano Flooring to re-seal the 4th floor walkway. The work will begin on Tuesday, July 11th and conclude on Monday, July 17th. Please note the map below for the impacts to your specific Unit.
The project will begin with power washing. Please be careful when walking on the deck if it is wet. During the work, besides the power washing, the walkway will be inaccessible from 8:00 am – 5:00 pm due to the product needing to completely dry. All items in front of your door, including plants, welcome mats and decorations, must be removed prior to work commencing in your area.
Schedule:
July 11th and 12th – Power washing
July 12th and 13th – Section A (Units 420-426)
July 13th – Section B (Units 414-419)
July 14th – Section C (Units 401-404)
July 17th – Section E (Units 405-413)